Queens Street Tree Planting FY13 - Community Boards 1-8

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant trees in Community Boards 1-8 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2012
Projected Completion Date: December 2012
Completion Date: January 2013

Procurement

Start Date: January 2013
Projected Completion Date: October 2013
Completion Date: February 2013

Construction

Start Date: April 2013
Projected Completion Date: May 2014
Completion Date: March 2014

Understand how we build parks.

Funding

Total Funding: $1,509,000
Funding Sources:
  • City Council
  • Mayoral
  • Private

Location

Various locations, Queens

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024