Brooklyn Street Tree Planting FY13 - Community Boards 1-6,8,9,16
-
100% complete
-
100% complete
-
100% complete
This project will plant trees in Community Boards 1-4, 6, 8, 9, & 16 in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2012
Projected Completion Date:
December 2012
Completion Date:
January 2013
Procurement
Start Date: January 2013
Projected Completion Date:
October 2013
Completion
Date:
April 2013
Construction
Start Date: April 2013
Projected Completion Date:
April 2014
Completion Date: April 2014
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
- Private
Last updated: 11/22/2024