Brooklyn Street Tree Planting FY13 - Community Boards 5,16,17,18

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant trees in Community Boards 5 &16-18 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2012
Projected Completion Date: December 2012
Completion Date: July 2012

Procurement

Start Date: July 2012
Projected Completion Date: April 2013
Completion Date: February 2013

Construction

Start Date: March 2013
Projected Completion Date: March 2014
Completion Date: March 2014

Understand how we build parks.

Funding

Total Funding: $1,334,000
Funding Source: Mayoral