Brooklyn Street Tree Planting FY11 - Community Boards 7,10-15,17,18 (BG-511MR)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant street trees in Community Boards 7, 10-15, 17 and 18 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2012
Projected Completion Date: June 2013
Completion Date: November 2012

Procurement

Start Date: November 2012
Projected Completion Date: August 2013
Completion Date: May 2013

Construction

Start Date: September 2013
Projected Completion Date: September 2014
Completion Date: April 2015

Understand how we build parks.

Funding

Total Funding: $1,471,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations, Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025