Manhattan Street Tree Planting FY13

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant trees in Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2012
Projected Completion Date: December 2012
Completion Date: January 2013

Procurement

Start Date: January 2013
Projected Completion Date: October 2013
Completion Date: January 2013

Construction

Start Date: March 2013
Projected Completion Date: March 2014
Completion Date: January 2014

Understand how we build parks.

Funding

Total Funding: $1,598,000
Funding Sources:
  • City Council
  • Mayoral

Location

Various locations, Manhattan

Project Staff

Contact NYC Parks about this project