St. John's Park Sitting Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the outdoor sitting area adjacent to the recreation center in St. John’s Park, including new benches, fencing, picnic tables, game tables and chairs, a drinking fountain, flowering trees and ornamental plantings.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2011
Projected Completion Date: February 2012
Completion Date: October 2012

Procurement

Start Date: October 2012
Projected Completion Date: July 2013
Completion Date: September 2013

Construction

Start Date: May 2014
Projected Completion Date: May 2015
Completion Date: May 2015

Understand how we build parks.

Funding

Total Funding: $993,000
Funding Sources:
  • City Council
  • State

Location

St. John's Park, Brooklyn
Prospect Place between Troy Avenue and Schenectady Avenue
Community Board: 08

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024