Project Timeline
Design
Assigned & Start Date: July 2011
Projected Completion Date:
February 2012
Completion Date:
October 2012
Procurement
Start Date: October 2012
Projected Completion Date:
July 2013
Completion
Date:
September 2013
Construction
Start Date: May 2014
Projected Completion Date:
May 2015
Completion Date: May 2015
Understand how we build parks.
Funding
Funding Sources:
- City Council
- State
Location
St. John's Park, Brooklyn
Prospect Place between Troy Avenue and Schenectady Avenue
Community Board: 08
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024