Riverside Park Tiemann Place Stairs and Sidewalk Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the stairs and adjacent perimeter sidewalk between Tiemann Place and Riverside Drive in Riverside Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2011
Projected Completion Date:
June 2013
Completion Date:
October 2013
Procurement
Start Date: October 2013
Projected Completion Date:
July 2014
Completion
Date:
June 2014
Construction
Start Date: July 2014
Projected Completion Date:
July 2015
Completion Date: June 2015
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Riverside Park, Manhattan
Tiemann Place and Riverside Drive
Community Board: 07, 09
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024