Sutton Place Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct a portion of Sutton Place Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2012
Projected Completion Date: September 2013
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: May 2017

Construction

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $1,750,000
Funding Sources:
  • City Council
  • Private

Location

Sutton Place Park, Manhattan
FDR Drive between 56th and 57th Streets
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024