Design
Assigned & Start Date: April 2012
Projected Completion Date:
September 2013
Completion Date:
September 2015
Procurement
Start Date: September 2015
Projected Completion Date:
June 2016
Completion
Date:
May 2017
Construction
Start Date: June 2017
Projected Completion Date:
June 2018
Completion Date: July 2019