Belt Parkway Landscape Restoration and Tree Planting at Canarsie
-
100% complete
-
100% complete
-
100% complete
This project will restore trees, preserve and re-establish the historic character of the parkway for drivers and pedestrians, enhance the visual cohesiveness of the parkway, and restore habitat along the Belt Parkway.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2014
Projected Completion Date:
April 2015
Completion Date:
May 2015
Procurement
Start Date: May 2015
Projected Completion Date:
February 2016
Completion
Date:
March 2016
Construction
Start Date: September 2016
Projected Completion Date:
September 2019
Completion Date: June 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Belt Parkway/Shore Parkway, Brooklyn
Belt Parkway at Paerdegat Basin Bridge, Rockaway Park Bridge and Fresh Creek Basin Bridge
Community Board: 05, 10, 11, 13, 15, 18, 10
Project Staff
Contact NYC Parks about this projectLast updated: 01/17/2025