Belt Parkway Landscape Restoration and Tree Planting at Canarsie

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will restore trees, preserve and re-establish the historic character of the parkway for drivers and pedestrians, enhance the visual cohesiveness of the parkway, and restore habitat along the Belt Parkway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2014
Projected Completion Date: April 2015
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: February 2016
Completion Date: March 2016

Construction

Start Date: September 2016
Projected Completion Date: September 2019
Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $6,284,000
Funding Source: Mayoral

Location

Belt Parkway/Shore Parkway, Brooklyn
Belt Parkway at Paerdegat Basin Bridge, Rockaway Park Bridge and Fresh Creek Basin Bridge
Community Board: 05, 10, 11, 13, 15, 18, 10

 