Morris-Jumel Mansion Streetscape Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will provide an opportunity to strengthen the historic character and elegance of the existing landscape. The project will create a new entrance to the park and house that will comply with current ADA accessibility standards, improving access to the park. The perimeter sidewalk adjacent to the sections of wall being restored will be reconstructed, as will portions of the brick pathways in the park that lead to the mansion to provide a safe path for all visitors.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2012
Projected Completion Date:
March 2013
Completion Date:
July 2013
Procurement
Start Date: July 2013
Projected Completion Date:
April 2014
Completion
Date:
June 2014
Construction
Start Date: July 2014
Projected Completion Date:
July 2015
Completion Date: February 2016
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
Roger Morris Park, Manhattan
West 160th Street and Edgecombe Avenue, Manhattan
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025