Morris-Jumel Mansion Streetscape Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will provide an opportunity to strengthen the historic character and elegance of the existing landscape. The project will create a new entrance to the park and house that will comply with current ADA accessibility standards, improving access to the park. The perimeter sidewalk adjacent to the sections of wall being restored will be reconstructed, as will portions of the brick pathways in the park that lead to the mansion to provide a safe path for all visitors.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2012
Projected Completion Date: March 2013
Completion Date: July 2013

Procurement

Start Date: July 2013
Projected Completion Date: April 2014
Completion Date: June 2014

Construction

Start Date: July 2014
Projected Completion Date: July 2015
Completion Date: February 2016

Understand how we build parks.

Funding

Total Funding: $2,943,000
Funding Sources:
  • Mayoral
  • State

Location

Roger Morris Park, Manhattan
West 160th Street and Edgecombe Avenue, Manhattan
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024