Douglaston Golf Course Net Barrier Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install net fencing at Douglaston Park Golf Course.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2012
Projected Completion Date: January 2013
Completion Date: March 2013

Procurement

Start Date: March 2013
Projected Completion Date: December 2013
Completion Date: December 2013

Construction

Start Date: March 2014
Projected Completion Date: March 2015
Completion Date: July 2014

Understand how we build parks.

Funding

Total Funding: $175,000
Funding Sources:
  • City Council
  • Mayoral

Location

Douglaston Park Golf Course, Queens
Commonwealth Boulevard between Grand Central Parkway and 246th Street.
Community Board: 11

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024