Roy Wilkins Recreation Center Kitchen and Roof Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the kitchen, gymnasium roof, exterior waterproofing and site drainage at Roy Wilkins Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2011
Projected Completion Date:
March 2014
Completion Date:
April 2016
Procurement
Start Date: April 2016
Projected Completion Date:
January 2017
Completion
Date:
November 2017
Construction
Start Date: March 2018
Projected Completion Date:
September 2019
Completion Date: August 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Roy Wilkins Recreation Center, Queens
Baisley Boulevard and 177th Street
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project