Cedar Grove Beach Access Improvements

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roads and paths at Cedar Grove Beach in Great Kills Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2011
Projected Completion Date: June 2012
Completion Date: September 2012

Procurement

Start Date: September 2012
Projected Completion Date: June 2013
Completion Date: May 2013

Construction

Start Date: June 2014
Projected Completion Date: June 2015
Completion Date: May 2015

Understand how we build parks.

Funding

Total Funding: $343,000
Funding Source: City Council

Location

Great Kills Park, Staten Island
Cedar Grove Beach Place
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024