Design
Assigned & Start Date: March 2012
Projected Completion Date:
March 2015
Completion Date:
January 2016
Procurement
Start Date: January 2016
Projected Completion Date:
October 2016
Completion
Date:
February 2017
Construction
Start Date: June 2017
Projected Completion Date:
June 2018
Completion Date: May 2018
Understand how we build parks.
Funding
Funding Source: City Council
Locations
-
Charlton Plaza, Manhattan
Ave. of Americas, King St. and Charlton St.
Community Board: 02 -
Father Fagan Park, Manhattan
Ave. Of Americas between Prince St. & Spring St.
Community Board: 02
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025