Olmsted Center Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the Olmsted Center in Flushing Meadows Corona Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2010
Projected Completion Date:
August 2013
Completion Date:
June 2014
Procurement
Start Date: June 2014
Projected Completion Date:
March 2015
Completion
Date:
February 2015
Construction
Start Date: May 2015
Projected Completion Date:
October 2016
Completion Date: January 2022
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Flushing Meadows Corona Park, Queens
117-02 Roosevelt Avenue
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project