McCarren Park Pool & Bath House Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pool and bathhouse at McCarren Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2007
Projected Completion Date: November 2008
Completion Date: June 2009

Procurement

Start Date: June 2009
Projected Completion Date: March 2010
Completion Date: December 2009

Construction

Start Date: January 2010
Projected Completion Date: January 2012
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $54,622,000
Funding Sources:
  • City Council
  • Mayoral

Location

McCarren Park, Brooklyn
Lorimer Street between Bayard Street and Driggs Avenue
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025