McCarren Park Pool & Bath House Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the pool and bathhouse at McCarren Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2007
Projected Completion Date:
November 2008
Completion Date:
June 2009
Procurement
Start Date: June 2009
Projected Completion Date:
March 2010
Completion
Date:
December 2009
Construction
Start Date: January 2010
Projected Completion Date:
January 2012
Completion Date: June 2014