PFC Norton Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building at PFC Norton Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2006
Completion Date: February 2010

Procurement

Start Date: February 2010
Projected Completion Date: October 2010
Completion Date: June 2011

Construction

Start Date: March 2012
Projected Completion Date: December 2012
Completion Date: November 2014

Understand how we build parks.

Funding

Total Funding: $738,000
Funding Source: City Council

Location

Pfc Norton Playground, Brooklyn
Nostrand Avenue between Kings Highway and Avenue P
Community Board: 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024