PFC Norton Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building at PFC Norton Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2006
Completion Date:
February 2010
Procurement
Start Date: February 2010
Projected Completion Date:
October 2010
Completion
Date:
June 2011
Construction
Start Date: March 2012
Projected Completion Date:
December 2012
Completion Date: November 2014
Understand how we build parks.
Funding
Funding Source: City Council
Location
Pfc Norton Playground, Brooklyn
Nostrand Avenue between Kings Highway and Avenue P
Community Board: 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025