Ferry Point Community Park Public Restroom Building Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a public restroom building in the eastern section of Ferry Point Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2008
Completion Date:
June 2012
Procurement
Start Date: June 2012
Projected Completion Date:
February 2013
Completion
Date:
April 2013
Construction
Start Date: July 2013
Projected Completion Date:
July 2014
Completion Date: July 2015
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Ferry Point Park, Bronx
Balcom Avenue and Dewey Avenue
Community Board: 10
Project Staff
Project Liaison: Katerine Borrome