Ferry Point Community Park Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a public restroom building in the eastern section of Ferry Point Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2008
Completion Date: June 2012

Procurement

Start Date: June 2012
Projected Completion Date: February 2013
Completion Date: April 2013

Construction

Start Date: July 2013
Projected Completion Date: July 2014
Completion Date: July 2015

Understand how we build parks.

Funding

Total Funding: $1,331,000
Funding Source: Mayoral

Location

Ferry Point Park, Bronx
Balcom Avenue and Dewey Avenue
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024