Williamsbridge Oval Recreation Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the recreation building at Williamsbridge Oval Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2007
Projected Completion Date: September 2007
Completion Date: May 2008

Procurement

Start Date: May 2008
Projected Completion Date: February 2009
Completion Date: August 2009

Construction

Start Date: April 2010
Projected Completion Date: May 2011
Completion Date: November 2013

Understand how we build parks.

Funding

Total Funding: $5,346,000
Funding Source: Mayoral

Location

Williamsbridge Oval, Bronx
Van Cortlandt Avenue East and Reservoir Oval
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project