Williamsbridge Oval Recreation Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the recreation building at Williamsbridge Oval Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2007
Projected Completion Date:
September 2007
Completion Date:
May 2008
Procurement
Start Date: May 2008
Projected Completion Date:
February 2009
Completion
Date:
August 2009
Construction
Start Date: April 2010
Projected Completion Date:
May 2011
Completion Date: November 2013
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Williamsbridge Oval, Bronx
Van Cortlandt Avenue East and Reservoir Oval
Community Board: 07
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project