Andrew Haswell Green Searail and Rooftop Sitting Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a rooftop sitting area and searail in East River Esplanade.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2008
Projected Completion Date: December 2012
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: June 2015

Construction

Start Date: August 2015
Projected Completion Date: January 2017
Completion Date: January 2017

Understand how we build parks.

Funding

Total Funding: $4,635,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral
  • State

Location

Andrew Haswell Green Park, Manhattan
FDR Drive between East 60th Street and East 62nd Street
Community Board: 08

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024