Marcus Garvey Park Fire Watchtower Dismantling
-
100% complete
-
100% complete
-
100% complete
This project will dismantle the Marcus Garvey Park Fire Watchtower in preparation for its reconstruction.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2013
Projected Completion Date:
January 2014
Completion Date:
June 2014
Procurement
Start Date: June 2014
Projected Completion Date:
March 2015
Completion
Date:
November 2014
Construction
Start Date: August 2014
Projected Completion Date:
February 2015
Completion Date: June 2015
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Private
Location
Marcus Garvey Park, Manhattan
Madison Avenue, East 124th Street, Mount Morris Park West, West 120th Street
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025