Battery Town Green and Battery Bikeway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct lawns and bikeway at the Battery.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2008
Projected Completion Date: July 2010
Completion Date: September 2011

Procurement

Start Date: September 2011
Projected Completion Date: June 2012
Completion Date: July 2012

Construction

Start Date: September 2012
Projected Completion Date: March 2014
Completion Date: October 2015

Understand how we build parks.

Funding

Total Funding: $15,698,000
Funding Sources:
  • Federal
  • Private
  • State

Location

The Battery, Manhattan
State Street and Battery Place
Community Board: 01

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024