Battery Town Green and Battery Bikeway Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct lawns and bikeway at the Battery.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2008
Projected Completion Date:
July 2010
Completion Date:
September 2011
Procurement
Start Date: September 2011
Projected Completion Date:
June 2012
Completion
Date:
July 2012
Construction
Start Date: September 2012
Projected Completion Date:
March 2014
Completion Date: October 2015
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Private
- State
Location
The Battery, Manhattan
State Street and Battery Place
Community Board: 01
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024