Harry Maze Playground Security Lighting Installation
-
100% complete
-
100% complete
-
100% complete
This project will install security lighting in Harry Maze Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2010
Projected Completion Date:
September 2013
Completion Date:
March 2015
Procurement
Start Date: March 2015
Projected Completion Date:
November 2015
Completion
Date:
June 2016
Construction
Start Date: September 2016
Projected Completion Date:
September 2017
Completion Date: May 2017
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
Harry Maze Playground, Brooklyn
Avenue D between 56th Street and 57th Street
Community Board: 17
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025