44th Drive Pier Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the 44th Drive Pier and DEP sewer outfall.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2008
Projected Completion Date:
February 2013
Completion Date:
July 2014
Procurement
Start Date: July 2014
Projected Completion Date:
April 2015
Completion
Date:
July 2015
Construction
Start Date: September 2015
Projected Completion Date:
March 2017
Completion Date: August 2016
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
East River and 44th Drive
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025