44th Drive Pier Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the 44th Drive Pier and DEP sewer outfall.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2008
Projected Completion Date: February 2013
Completion Date: July 2014

Procurement

Start Date: July 2014
Projected Completion Date: April 2015
Completion Date: July 2015

Construction

Start Date: September 2015
Projected Completion Date: March 2017
Completion Date: August 2016

Understand how we build parks.

Funding

Total Funding: $8,125,000
Funding Source: Mayoral

Location

East River and 44th Drive

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024