Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roofing systems at various parks facilities in Brooklyn and Staten Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2006
Completion Date: March 2009

Procurement

Start Date: March 2009
Projected Completion Date: December 2009
Completion Date: January 2010

Construction

Start Date: March 2010
Projected Completion Date: February 2013
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $3,325,000
Funding Source: Mayoral