Brooklyn and Queens Recreation and Nature Centers HVAC Systems Reconstruction (CNYG-1910MA1)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct HVAC systems at Lost Battalion Hall Recreation Center and Brownsville Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2010
Projected Completion Date:
September 2013
Completion Date:
January 2014
Procurement
Start Date: January 2014
Projected Completion Date:
October 2014
Completion
Date:
August 2015
Construction
Start Date: November 2015
Projected Completion Date:
October 2018
Completion Date: October 2018
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Locations
-
Brownsville Playground, Brooklyn
Hegeman Ave., Linden Blvd. bet. Powell St. and Mother Gaston Blvd.
Community Board: 16 -
Lost Battalion Hall Recreation Center, Queens
Queens Blvd. Bet 62 Ave. and 62 Rd.
Community Board: 06
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025