Bronx and Manhattan Recreation and Nature Center HVAC Repair (CNYG-1810MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the HVAC systems for recreation centers and nature centers at parks locations in the Bronx and Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2010
Completion Date: November 2011

Procurement

Start Date: November 2011
Projected Completion Date: July 2012
Completion Date: February 2013

Construction

Start Date: April 2013
Projected Completion Date: March 2016
Completion Date: July 2015

Understand how we build parks.

Funding

Total Funding: $255,000
Funding Sources:
  • City Council
  • Mayoral

Location

Williamsbridge Oval, Bronx
Van Cortlandt Ave. East, Resevoir Oval E
Community Board: 07

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024