Bronx and Manhattan Recreation and Nature Center HVAC Repair (CNYG-1810MA)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the HVAC systems for recreation centers and nature centers at parks locations in the Bronx and Manhattan.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2010
Completion Date:
November 2011
Procurement
Start Date: November 2011
Projected Completion Date:
July 2012
Completion
Date:
February 2013
Construction
Start Date: April 2013
Projected Completion Date:
March 2016
Completion Date: July 2015
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Williamsbridge Oval, Bronx
Van Cortlandt Ave. East, Resevoir Oval E
Community Board: 07
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024