Citywide Recreation & Nature Centers Electrical System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the electrical systems at various recreation centers and nature centers citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2007
Completion Date: April 2007

Procurement

Start Date: April 2007
Projected Completion Date: January 2008
Completion Date: July 2008

Construction

Start Date: November 2008
Projected Completion Date: November 2010
Completion Date: March 2014

Understand how we build parks.

Funding

Total Funding: $351,000
Funding Source: Mayoral