Citywide Recreation & Nature Centers Electrical System Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the electrical systems at various recreation centers and nature centers citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2007
Completion Date:
April 2007
Procurement
Start Date: April 2007
Projected Completion Date:
January 2008
Completion
Date:
July 2008
Construction
Start Date: November 2008
Projected Completion Date:
November 2010
Completion Date: March 2014
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Various locations
Project Staff
Project Liaison: Cristin Leoutsakos