Citywide Pool Structural Systems Reconstruction (CNYG-1011M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct deteriorated structural systems at park and pool facilities citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2011
Completion Date: March 2011

Procurement

Start Date: March 2011
Projected Completion Date: November 2011
Completion Date: August 2013

Construction

Start Date: September 2013
Projected Completion Date: September 2016
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $2,419,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024