Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2010
Completion Date:
January 2011
Procurement
Start Date: January 2011
Projected Completion Date:
October 2011
Completion
Date:
August 2011
Construction
Start Date: September 2011
Projected Completion Date:
December 2013
Completion Date: December 2013