Brooklyn and Staten Island Street Tree Planting FY10

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in parks and playgrounds in Brooklyn and Staten Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2010
Completion Date: January 2011

Procurement

Start Date: January 2011
Projected Completion Date: October 2011
Completion Date: August 2011

Construction

Start Date: September 2011
Projected Completion Date: December 2013
Completion Date: December 2013

Understand how we build parks.

Funding

Total Funding: $1,166,000
Funding Source: Mayoral

Location

Various locations in Brooklyn and Staten Island.

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024