University Park Stairway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct stairways and landings in University Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2008
Projected Completion Date: January 2009
Completion Date: December 2010

Procurement

Start Date: December 2010
Projected Completion Date: September 2011
Completion Date: July 2012

Construction

Start Date: August 2012
Projected Completion Date: February 2013
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $410,000
Funding Source: Mayoral

Location

University Woods, Bronx
Sedgwick to Cedar Avenues, North of West 180 Street
Community Board: 05

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024