Van Cortlandt Park Putnam Greenway Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a portion of the Putnam Greenway in Van Cortlandt Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2008
Projected Completion Date:
June 2016
Completion Date:
January 2018
Procurement
Start Date: January 2018
Projected Completion Date:
October 2018
Completion
Date:
April 2019
Construction
Start Date: August 2019
Projected Completion Date:
August 2020
Completion Date: October 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Federal
- Mayoral
Location
Van Cortlandt Park, Bronx
City line to Van Cortlandt Park South
Community Board: 07, 08, 12
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024