Van Cortlandt Park Putnam Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a portion of the Putnam Greenway in Van Cortlandt Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2008
Projected Completion Date: June 2016
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: April 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $3,783,000
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Location

Van Cortlandt Park, Bronx
City line to Van Cortlandt Park South
Community Board: 07, 08, 12

 