Soundview Park Running Track and Athletic Field Construction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the running track and athletic field in Soundview Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2010
Projected Completion Date:
November 2010
Completion Date:
February 2011
Procurement
Start Date: February 2011
Projected Completion Date:
October 2011
Completion
Date:
January 2012
Construction
Start Date: March 2012
Projected Completion Date:
March 2013
Completion Date: June 2014