Soundview Park Playground and Sports Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, spray shower, lawn, and basketball and handball courts at Soundview Park with new play equipment, planting, and lighting.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2007
Projected Completion Date: January 2012
Completion Date: February 2012

Procurement

Start Date: February 2012
Projected Completion Date: October 2012
Completion Date: March 2013

Construction

Start Date: May 2013
Projected Completion Date: October 2014
Completion Date: May 2017

Understand how we build parks.

Funding

Total Funding: $4,193,000
Funding Sources:
  • City Council
  • Mayoral

Location

Soundview Park, Bronx
Metcalf Avenue and Seward Avenue
Community Board: 09

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025