Soundview Park Playground and Sports Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground, spray shower, lawn, and basketball and handball courts at Soundview Park with new play equipment, planting, and lighting.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2007
Projected Completion Date:
January 2012
Completion Date:
February 2012
Procurement
Start Date: February 2012
Projected Completion Date:
October 2012
Completion
Date:
March 2013
Construction
Start Date: May 2013
Projected Completion Date:
October 2014
Completion Date: May 2017
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Soundview Park, Bronx
Metcalf Avenue and Seward Avenue
Community Board: 09
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025