Bronx General Site Work (XG-410M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct play equipment, safety surfacing, pavements, and handball courts at various parks in the Bronx.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2009
Completion Date:
April 2010
Procurement
Start Date: April 2010
Projected Completion Date:
January 2011
Completion
Date:
October 2011
Construction
Start Date: December 2011
Projected Completion Date:
June 2013
Completion Date: September 2013
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Crotona Park, Bronx
Crotona Park North to South, Fulton Av to Southern Blvd & Crotona Park East
Community Board: 03 -
Haffen Park, Bronx
Hammersley Ave. to Burke Ave. bet. Ely Ave. and Gunther Ave.
Community Board: 12 -
Merriam Playground, Bronx
W. 168 St. bet. Dr. MLK Jr. Blvd. and Merriam Ave.
Community Board: 04 -
Morgan Playground, Bronx
E 168 St bet Park Av & Washington Av
Community Board: 03 -
Washington's Walk, Bronx
Resevoir Av bet Sedgwick Av & Goulden Av
Community Board: 08
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025