Bronx River Park Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct an existing portion and construct a new portion of the Bronx River Greenway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2010
Projected Completion Date: January 2014
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: September 2015

Construction

Start Date: November 2015
Projected Completion Date: February 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $2,899,000
Funding Sources:
  • Borough President
  • City Council
  • Federal

Location

Bronx Park, Bronx
Unionport Road and Allerton Avenue
Community Board: 06, 07, 11, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024