Bronx River Park Greenway Construction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct an existing portion and construct a new portion of the Bronx River Greenway.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2010
Projected Completion Date:
January 2014
Completion Date:
October 2014
Procurement
Start Date: October 2014
Projected Completion Date:
July 2015
Completion
Date:
September 2015
Construction
Start Date: November 2015
Projected Completion Date:
February 2017
Completion Date: June 2017
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Federal
Location
Bronx Park, Bronx
Unionport Road and Allerton Avenue
Community Board: 06, 07, 11, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025