Yolanda Garcia Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct Yolanda Garcia Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2008
Projected Completion Date: November 2013
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: February 2016
Completion Date: July 2016

Construction

Start Date: October 2016
Projected Completion Date: September 2019
Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $6,114,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Yolanda GarcĂ­a Park, Bronx
Melrose Avenue between East 159th and East 160th Streets
Community Board: 03

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024