Ferry Point Park Passive Waterfront Path and Landscape Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a waterfront path and salt water marsh in Ferry Point Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2015
Projected Completion Date:
September 2017
Completion Date:
December 2017
Procurement
Start Date: December 2017
Projected Completion Date:
August 2018
Completion
Date:
June 2019
Construction
Start Date: September 2019
Projected Completion Date:
March 2021
Completion Date: March 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Ferry Point Park, Bronx
East River between Emerson Avenue and the Bronx-Whitestone Bridge
Community Board: 10
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024