Ferry Point Park Passive Waterfront Path and Landscape Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a waterfront path and salt water marsh in Ferry Point Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2015
Projected Completion Date: September 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: August 2018
Completion Date: June 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2021
Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $11,736,000
Funding Source: Mayoral

Location

Ferry Point Park, Bronx
East River between Emerson Avenue and the Bronx-Whitestone Bridge
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024