Ewen Park Tot Lot Construction and Basketball Court Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct a basketball court and construct a tot lot and miscellaneous site work in Ewen Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2011
Projected Completion Date:
May 2014
Completion Date:
September 2014
Procurement
Start Date: September 2014
Projected Completion Date:
June 2015
Completion
Date:
July 2015
Construction
Start Date: September 2015
Projected Completion Date:
September 2016
Completion Date: December 2016
Understand how we build parks.
Funding
Funding Source: City Council
Location
Ewen Park, Bronx
Johnson Avenue, West 232nd Street and Riverdale Avenue, the Bronx
Community Board: 08
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024