Ewen Park Tot Lot Construction and Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct a basketball court and construct a tot lot and miscellaneous site work in Ewen Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2011
Projected Completion Date: May 2014
Completion Date: September 2014

Procurement

Start Date: September 2014
Projected Completion Date: June 2015
Completion Date: July 2015

Construction

Start Date: September 2015
Projected Completion Date: September 2016
Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $997,000
Funding Source: City Council

Location

Ewen Park, Bronx
Johnson Avenue, West 232nd Street and Riverdale Avenue, the Bronx
Community Board: 08

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024