Crotona Park Bathhouse Entrance Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the entrance towers, mezzanine roof and bridge at the entrance to the Crotona Park Bathhouse.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2010
Projected Completion Date:
October 2012
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
June 2018
Construction
Start Date: September 2018
Projected Completion Date:
December 2019
Completion Date: March 2021
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Crotona Park, Bronx
Fulton Avenue and East 173rd Street
Community Board: 03
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project