Crotona Park Bathhouse Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the entrance towers, mezzanine roof and bridge at the entrance to the Crotona Park Bathhouse.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2010
Projected Completion Date: October 2012
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: June 2018

Construction

Start Date: September 2018
Projected Completion Date: December 2019
Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $2,816,000
Funding Sources:
  • City Council
  • Mayoral

Location

Crotona Park, Bronx
Fulton Avenue and East 173rd Street
Community Board: 03

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024