Old Croton Aqueduct Signage Installation
-
100% complete
-
100% complete
-
100% complete
This project will construct signage at several locations along the Old Croton Aqueduct.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2010
Projected Completion Date:
June 2012
Completion Date:
September 2015
Procurement
Start Date: September 2015
Projected Completion Date:
June 2016
Completion
Date:
June 2016
Construction
Start Date: July 2016
Projected Completion Date:
July 2017
Completion Date: April 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Aqueduct Walk, Bronx
Aqueduct Ave. W. bet. W. Fordham Rd. and W. Kingsbridge Rd.
Community Board: 07 -
Aqueduct Walk, Bronx
East Burnside Avenue, University Avenue, Morton Place, Harrison Avenue
Community Board: 05, 07 -
Highbridge Park, Bronx
Dr. MLK Jr. Blvd. at W. 170 St.
Community Board: 04 -
Jerome Park, Bronx
Goulden Av bet W 205 St and Sedgwick Av
Community Board: 08 -
University Malls, Bronx
University Av bet W 174 St & W Tremont Av
Community Board: 05 -
Van Cortlandt Park, Bronx
NYC - Westchester County Line, Van Cortlandt Park S. bet. Broadway and Jerome Ave.
Community Board: 07, 08, 12
Project Staff
Project Liaison: Contact Us
Contact NYC Parks
about this project
Last updated: 01/17/2025