Pugsley Creek Park Basketball Court Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a basketball court in Pugsley Creek Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2010
Projected Completion Date:
April 2013
Completion Date:
June 2013
Procurement
Start Date: June 2013
Projected Completion Date:
March 2014
Completion
Date:
November 2014
Construction
Start Date: January 2015
Projected Completion Date:
January 2016
Completion Date: June 2016
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Pugsley Creek Park, Bronx
White Plains Road and Patterson Avenue
Community Board: 09
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project