Pelham Parkway Malls Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Pelham Parkway Malls between Boston Road and Wallace Avenue in the Bronx.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2013
Projected Completion Date: June 2014
Completion Date: April 2015

Procurement

Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: February 2016

Construction

Start Date: March 2016
Projected Completion Date: March 2018
Completion Date: November 2017

Understand how we build parks.

Funding

Total Funding: $1,434,000
Funding Source: Mayoral

Location

Pelham Parkway, Bronx
Boston Road and Wallace Avenue
Community Board: 11

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project