Aqueduct Walk 182nd Place Pathway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install new pavements, curbs and fencing as well as reconstruct an existing staircase. Plantings, trees and benches will be installed to complete the elevated walk experience.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2011
Completion Date: January 2012

Procurement

Start Date: January 2012
Projected Completion Date: October 2012
Completion Date: December 2012

Construction

Start Date: February 2013
Projected Completion Date: August 2014
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $3,858,000
Funding Source: Mayoral

Location

Aqueduct Walk, Bronx
Kingsbridge Road and West 182nd Place, the Bronx
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025