Aqueduct Walk 182nd Place Pathway Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will install new pavements, curbs and fencing as well as reconstruct an existing staircase. Plantings, trees and benches will be installed to complete the elevated walk experience.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2011
Completion Date:
January 2012
Procurement
Start Date: January 2012
Projected Completion Date:
October 2012
Completion
Date:
December 2012
Construction
Start Date: February 2013
Projected Completion Date:
August 2014
Completion Date: June 2014
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Aqueduct Walk, Bronx
Kingsbridge Road and West 182nd Place, the Bronx
Community Board: 07
Project Staff
Project Liaison: Katerine Borrome