Jerome Park Reservoir Jogging Trail Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a 5-foot wide jogging trail around the perimeter of the Jerome Park Reservoir, with new seating, plantings and adult fitness equipment. The project will also reconstruct the jogging trail, dog run, and basketball courts at Fort Independence Park, and construct new adult fitness equipment.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2007
Projected Completion Date:
April 2012
Completion Date:
April 2012
Procurement
Start Date: April 2012
Projected Completion Date:
January 2013
Completion
Date:
March 2013
Construction
Start Date: April 2013
Projected Completion Date:
April 2014
Completion Date: December 2014
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Jerome Park, Bronx
Goulden Avenue, Reservoir Avenue, Sedgwick Avenue
Community Board: 08
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024