Jerome Park Reservoir Jogging Trail Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a 5-foot wide jogging trail around the perimeter of the Jerome Park Reservoir, with new seating, plantings and adult fitness equipment. The project will also reconstruct the jogging trail, dog run, and basketball courts at Fort Independence Park, and construct new adult fitness equipment.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2007
Projected Completion Date: April 2012
Completion Date: April 2012

Procurement

Start Date: April 2012
Projected Completion Date: January 2013
Completion Date: March 2013

Construction

Start Date: April 2013
Projected Completion Date: April 2014
Completion Date: December 2014

Understand how we build parks.

Funding

Total Funding: $3,365,000
Funding Source: Mayoral

Location

Jerome Park, Bronx
Goulden Avenue, Reservoir Avenue, Sedgwick Avenue
Community Board: 08

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project