Aqueduct Walk 182nd Street Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a Public Restroom Building in Aqueduct Walk.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2006
Projected Completion Date: December 2013
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: February 2016
Completion Date: July 2016

Construction

Start Date: September 2016
Projected Completion Date: March 2018
Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $1,238,000
Funding Source: Mayoral

Location

Aqueduct Walk, Bronx
Aqueduct Avenue East between West 182nd Street and West 183rd Street
Community Board: 05, 07

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project