Pelham Bay Park Waterfront Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct and restore the shoreline, remove invasive plants, and construct a new pathway to improve public access to the waterfront at Pelham Bay Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2007
Projected Completion Date: March 2012
Completion Date: August 2013

Procurement

Start Date: August 2013
Projected Completion Date: May 2014
Completion Date: March 2014

Construction

Start Date: August 2014
Projected Completion Date: August 2015
Completion Date: September 2015

Understand how we build parks.

Funding

Total Funding: $1,040,000
Funding Source: Mayoral

Location

Pelham Bay Park, Bronx
Eastchester Bay between Pelham Bay landfill and Watt Avenue
Community Board: 10, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024