Hutchinson River Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a portion of the Hutchinson River Greenway from Pelham Parkway to Shore Road.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2007
Projected Completion Date: October 2007
Completion Date: February 2011

Procurement

Start Date: February 2011
Projected Completion Date: November 2011
Completion Date: August 2012

Construction

Start Date: September 2012
Projected Completion Date: June 2013
Completion Date: October 2013

Understand how we build parks.

Funding

Total Funding: $3,066,000
Funding Source: Mayoral

Location

Hutchinson River Parkway, Bronx
Pelham Parkway to Shore Road
Community Board: 10, 11

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024