Hutchinson River Greenway Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a portion of the Hutchinson River Greenway from Pelham Parkway to Shore Road.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2007
Projected Completion Date:
October 2007
Completion Date:
February 2011
Procurement
Start Date: February 2011
Projected Completion Date:
November 2011
Completion
Date:
August 2012
Construction
Start Date: September 2012
Projected Completion Date:
June 2013
Completion Date: October 2013
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Hutchinson River Parkway, Bronx
Pelham Parkway to Shore Road
Community Board: 10, 11
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025