Crotona Park Nature Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the nature center in Crotona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2013
Projected Completion Date: February 2015
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: November 2017

Construction

Start Date: March 2018
Projected Completion Date: September 2019
Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $3,279,000
Funding Sources:
  • City Council
  • Mayoral

Location

Crotona Park, Bronx
Crotona Avenue and Crotona Park East
Community Board: 03

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025