Bronx River Greenway Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a portion of the Bronx River Greenway between Soundview Park at Lafayette Ave & Bruckner Blvd.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2005
Projected Completion Date:
December 2007
Completion Date:
February 2011
Procurement
Start Date: February 2011
Projected Completion Date:
October 2011
Completion
Date:
July 2013
Construction
Start Date: October 2013
Projected Completion Date:
September 2014
Completion Date: August 2014
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Locations
-
Soundview Park, Bronx
Bronx River, Lafayette, Metcalf, Bronx River Avenues
Community Board: 09 - DOT (Non-Parks) Property in the Bronx
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024