Bronx River Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a portion of the Bronx River Greenway between Soundview Park at Lafayette Ave & Bruckner Blvd.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2005
Projected Completion Date: December 2007
Completion Date: February 2011

Procurement

Start Date: February 2011
Projected Completion Date: October 2011
Completion Date: July 2013

Construction

Start Date: October 2013
Projected Completion Date: September 2014
Completion Date: August 2014

Understand how we build parks.

Funding

Total Funding: $1,885,000
Funding Sources:
  • Federal
  • Mayoral

Locations

  • Soundview Park, Bronx
    Bronx River, Lafayette, Metcalf, Bronx River Avenues
    Community Board: 09
  • DOT (Non-Parks) Property in the Bronx
 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024